Facility Alerts and Updates
Find information on alerts, closures and hazards for trails, parks and facilities operated by Columbus Recreation and Parks Department.

Update
This is used to identify general updates at a facility.

Hazard
This is used to advise caution at facilities that are still open.

Closure
This is used to identify facilities that are closed.
Active Updates

All Parks and Trails
Some parks and trails still have debris and damage from the Aug. 11 storm. Our team is out working to clean up after the storm; however, with the extent of the damage, this will take some time. Residents are encouraged to be cautious in parks and on trails – pay attention to any posted closures and warning signs.

Barack Community Center
Closure started on Aug. 11, 2026
Due to storm damage, Barack Community Center is closed. More information will be shared as work continues; find the most recent updates.

Beatty Community Center
Closure started in August 2024
The investigation concluded that the fire at Beatty Community Center in August 2024 was accidental. We are preparing to begin the cleanup and mitigation process to address the fire and water damage. While the damage was primarily isolated to the gymnasium, we’re using this opportunity to make needed renovations to other areas of the center during the closure. Although it’s too early to provide a specific timeline for the work, we’ve relocated most of our programs to other sites to ensure we can continue serving the community with minimal disruption.

Duranceau Park
Closure started on May 25, 2026
The playground at Duranceau Park has been replaced due to unplanned safety concerns. When funding allows, a larger playground will be installed.

Franklin Park
Closure started on June 23, 2026
The Franklin Park Cascades is closed due to a leak in the lower pond. Work will begin shortly to design a solution and fix the problem.

Griggs Park
Closure started in July 2025
The Trabue-Murphy boat ramp is closed until further notice due to uneven subsurface conditions that could cause damage to boats. The department is working to address the issue.

Hauntz Park
Mid-2025 – Aug. 31, 2026
Hauntz Park will be renovated throughout the remainder of 2025 and into summer 2026. The park will be unsafe for resident access as construction progresses. With warmer weather, concrete work, placement of park lighting, park furnishings and wetland plantings will be completed in June. These timeframes are subject to unforeseen site conditions and weather.
A few final items remain at the park, sport court color coating, concrete repairs, site cleanup and final grading. This should take until mid-August

Mock Park
April 13, 2026 – End of 2027
Mock Park will be under construction for the Mock Road Connector trail, which will connect Alum Creek Trail to Mock Park and the existing Hudson Greenway Connector. There should be minimal disruptions to ongoing park activity. Construction will finish by the end of 2027.

Nelson Park
Jan. 13, 2026 – Sept. 22, 2026
Nelson Park will be receiving a new playground, and construction crews will be on-site. The outdated playground was removed. The new playground will be installed northeast of the shelterhouse. Park users are to exercise caution and avoid areas fenced off for construction.

Saunders Park
Feb. 2, 2026 – Sept. 4, 2026
A small portion of Saunders Park will be under construction beginning Feb. 1, 2026, as it will be receiving a new adult fitness circuit. During this time, park visitors are urged to use caution near any construction.

Willow Creek Park
Sept. 8-Sept. 15, 2026
Willow Creek Park will be temporarily closed from Sept. 8-Sept. 15 for demolition of a shelterhouse, playground and basketball court. This is preparing the site for future construction.